Harward Sewer and Pump Station Upgrade
To help prevent ongoing water pollution events, the City will replace and upgrade a major sewer main and pump station on Harward Street. This is part of a larger project to upgrade the City's aging sewer infrastructure using funds from a voter-approved bond in 2023.The Harward drainage area, the largest part of the Bath sewage system, consistently sees overflow problems in times when heavy rainfall outpaces the Water Pollution Control Facility's ability to pump out and treat the storm water and sewage .
To help prevent ongoing water pollution events, the City will replace and upgrade a major sewer main and pump station on Harward Street. This is part of a larger project to upgrade the City's aging sewer infrastructure using funds from a voter-approved bond in 2023.The Harward drainage area, the largest part of the Bath sewage system, consistently sees overflow problems in times when heavy rainfall outpaces the Water Pollution Control Facility's ability to pump out and treat the storm water and sewage .
-
Monthly Construction Update-March 2026
Share Monthly Construction Update-March 2026 on Facebook Share Monthly Construction Update-March 2026 on Twitter Share Monthly Construction Update-March 2026 on Linkedin Email Monthly Construction Update-March 2026 linkHarward Street Pump Station & Sewer Interceptor Upgrade Project – Community Update March 2026
Work Completed Last Month
Construction activity increased throughout March as sewer installation and supporting activities advanced along Washington Street and in cross-country areas. Crews continued ledge removal and blasting operations between Winship Street and Washington Street, while progressing installation of new 24” sewer pipe along Washington Street near the Harward Street Pump Station.
Preparations for the railroad crossing at Dike Newell School advanced, including delivery of casing pipe and excavation of the launch pit on the south side of the railroad near Dike Newell School. Crews have completed augering underneath the railroad track to install the new sewer line on 3/25.
A temporary bypass pumping system was finalized and placed into operation to maintain uninterrupted sewer service during construction. Coordination with nearby homeowners continued throughout the month to address drainage, driveway access, and erosion control concerns.
What’s Next
In addition, installation of the new 36-inch sewer pipe is expected to begin between CSO SMH 133 off the shoulder of Washington Street, and continue down Washington to SMH 137 in front of the Harward Street Pump Station. Railroad casing installation beneath the rail corridor is near complete.
Work in the coming weeks will focus on continued sewer installation along Washington Street near Harward Street. Bypass pumping is expected to remain in operation for several weeks while new sewer pipe is installed along Washington Street.
Crooker plans to complete blasting of ledge between Washington Street and Winship Street by the end of March, weather and subsurface conditions permitting. Notification will continue to be provided to affected residents in advance of blasting operations. Please contact the City or the Resident Project Representative for questions regarding upcoming blasting activities.
Initial construction of the pump station flood wall is anticipated to begin in April.
Traffic & Neighborhood Impacts
As sewer installation work progresses, residents may notice increased construction activity, including heavy equipment, blasting operations, and work within easement areas. Temporary traffic impacts are expected, particularly along Washington Street, where detours and lane closures will remain in place for the next few weeks to allow Crooker to safely complete sewer installation.
The City, contractor, and project team will continue coordinating directly with affected homeowners regarding driveway access, erosion control, landscaping, and property-specific concerns.
Looking Ahead
Once ledge removal and initial sewer installation are complete, sewer pipe installation work will continue upstream along the cross-country sewer alignment off of Washington Street. Major construction activities at the pump station site itself are still anticipated to begin later this year, with building construction currently scheduled for early summer.
The City of Bath, Wright-Pierce, and the contractor will continue working closely together to minimize disruptions and keep residents informed as construction progresses. Additional updates will be shared regularly as milestones are reached.
Harward Street Pump Station & Sewer Interceptor Upgrade Project – Community Update March 2026
Work Completed Last Month
Construction activity increased throughout March as sewer installation and supporting activities advanced along Washington Street and in cross-country areas. Crews continued ledge removal and blasting operations between Winship Street and Washington Street, while progressing installation of new 24” sewer pipe along Washington Street near the Harward Street Pump Station.
Preparations for the railroad crossing at Dike Newell School advanced, including delivery of casing pipe and excavation of the launch pit on the south side of the railroad near Dike Newell School. Crews have completed augering underneath the railroad track to install the new sewer line on 3/25.
A temporary bypass pumping system was finalized and placed into operation to maintain uninterrupted sewer service during construction. Coordination with nearby homeowners continued throughout the month to address drainage, driveway access, and erosion control concerns.
What’s Next
In addition, installation of the new 36-inch sewer pipe is expected to begin between CSO SMH 133 off the shoulder of Washington Street, and continue down Washington to SMH 137 in front of the Harward Street Pump Station. Railroad casing installation beneath the rail corridor is near complete.
Work in the coming weeks will focus on continued sewer installation along Washington Street near Harward Street. Bypass pumping is expected to remain in operation for several weeks while new sewer pipe is installed along Washington Street.
Crooker plans to complete blasting of ledge between Washington Street and Winship Street by the end of March, weather and subsurface conditions permitting. Notification will continue to be provided to affected residents in advance of blasting operations. Please contact the City or the Resident Project Representative for questions regarding upcoming blasting activities.
Initial construction of the pump station flood wall is anticipated to begin in April.
Traffic & Neighborhood Impacts
As sewer installation work progresses, residents may notice increased construction activity, including heavy equipment, blasting operations, and work within easement areas. Temporary traffic impacts are expected, particularly along Washington Street, where detours and lane closures will remain in place for the next few weeks to allow Crooker to safely complete sewer installation.
The City, contractor, and project team will continue coordinating directly with affected homeowners regarding driveway access, erosion control, landscaping, and property-specific concerns.
Looking Ahead
Once ledge removal and initial sewer installation are complete, sewer pipe installation work will continue upstream along the cross-country sewer alignment off of Washington Street. Major construction activities at the pump station site itself are still anticipated to begin later this year, with building construction currently scheduled for early summer.
The City of Bath, Wright-Pierce, and the contractor will continue working closely together to minimize disruptions and keep residents informed as construction progresses. Additional updates will be shared regularly as milestones are reached.
Timeline
-
2022
Harward Sewer and Pump Station Upgrade has finished this stageHarward Street pump station upgrade identified as a crucial need in the 2022 Combined Sewer Overflow (CSO) Master Plan
-
2024
Harward Sewer and Pump Station Upgrade has finished this stageDesign and Permitting is completed for the Pump Station Upgrade including:
- New Generator
- New Electrical and Controls
- New Pumps (6.0 MGD)
- Floodproofing Design
- Ancillary Upgrades
- Upsizing Interceptor Sewer
- Relocating CSO
This work was done by Wright-Pierce Engineering
-
2025
Harward Sewer and Pump Station Upgrade has finished this stageAdditional permitting was completed and the project construction went out to bid. The City selected Crooker Construction as the winning bidder to complete the project.
-
Early 2026
Harward Sewer and Pump Station Upgrade is currently at this stage- Crooker will be physically locating all the structures along the route, to ensure property owners are aware as well as completing necessary Digsafe procedures.
- Equipment staging and Limb clearing and tree removal
- Drill sections of the corridor to determine ledge depth
- Sewer pipe replacement and bypass pumping begins at the Harward St pump station will move south down Washington Street.
Project Leaders
-
Phone 207-443-8348 Email blevitt@cityofbathmaine.gov -
Phone 207-443-8357 Email cwallace@cityofbathmaine.gov
Engineering and Construction
-
Phone 207-319-1511 -
-



