1. Washington Street (North of Harward St - 1500 ft. x 24 ft.): Remove 2-inches of existing pavement via cold-planing; shim to establish crown and cross-slope with 9.5 mm HMA; Surface with 1 ½ - inches 12.5 mm HMA.
2. Varney Mill Road (From North Bath Road - 1500 ft. x 24 ft.): Remove 2-inches of existing pavement via cold-planing; shim to establish crown and cross-slope with 9.5 mm HMA; Surface with 1 ½ - inches 12.5 mm HMA.
3. Spruce Street (Total with approximately 110' of Federal St) off of High St - 900 ft. x 21 ft.: Remove 2-inches of existing pavement via cold-planing; shim to establish crown and cross-slope with 9 .5 mm HMA; Surface with 1 ½ - inches 12.5 mm HMA. (Bid Alternate for 640' of slip form concrete curb)
4. Lark St. (Full length - 575 ft. x 24 ft.):Remove 2-inches of existing pavement via cold-planing; shim to establish crown and cross-slope with 9.5 mm HMA; Surface with 1 ½ - inches 12.5 mm HMA.
5. Middle St. (South of Leeman Hwy to South St- 1200 ft. x 24 ft.): Remove 2- inches of existing pavement via cold-planing; shim to establish crown and
cross-slope with 9.5 mm HMA; Surface with 1 ½- inches 12.5 mm HMA.
6. Windjammer Way;(North of North Street 525' x 24' and 275' x 40'): Remove 2- inches of existing pavement via cold-planing; Shim to establish crown and crossslope with 9.5 mm HMA; Surface with 1 ½- inches 12.5mm HMA
1. Washington Street (North of Harward St - 1500 ft. x 24 ft.): Remove 2-inches of existing pavement via cold-planing; shim to establish crown and cross-slope with 9.5 mm HMA; Surface with 1 ½ - inches 12.5 mm HMA.
2. Varney Mill Road (From North Bath Road - 1500 ft. x 24 ft.): Remove 2-inches of existing pavement via cold-planing; shim to establish crown and cross-slope with 9.5 mm HMA; Surface with 1 ½ - inches 12.5 mm HMA.
3. Spruce Street (Total with approximately 110' of Federal St) off of High St - 900 ft. x 21 ft.: Remove 2-inches of existing pavement via cold-planing; shim to establish crown and cross-slope with 9 .5 mm HMA; Surface with 1 ½ - inches 12.5 mm HMA. (Bid Alternate for 640' of slip form concrete curb)
4. Lark St. (Full length - 575 ft. x 24 ft.):Remove 2-inches of existing pavement via cold-planing; shim to establish crown and cross-slope with 9.5 mm HMA; Surface with 1 ½ - inches 12.5 mm HMA.
5. Middle St. (South of Leeman Hwy to South St- 1200 ft. x 24 ft.): Remove 2- inches of existing pavement via cold-planing; shim to establish crown and
cross-slope with 9.5 mm HMA; Surface with 1 ½- inches 12.5 mm HMA.
6. Windjammer Way;(North of North Street 525' x 24' and 275' x 40'): Remove 2- inches of existing pavement via cold-planing; Shim to establish crown and crossslope with 9.5 mm HMA; Surface with 1 ½- inches 12.5mm HMA
Proposed Schedule for City of Bath – Street Paving – 2026-2027
Scope:
Lower and raise Manhole structures, mill 2” of existing pavement, shim to establish crown and cross-slope with 9.5 mm HMA, Surface with 1 ½ inches 12.5mm HMA
Monday 09/28/26 through Friday 10/02/26
Mobilize
Install traffic control
Lower MH on Windjammer Way, Middle Street, Lark Street
Monday 10/05/26 through Friday 10/09/26
Resume lowering MH on Spruce St. and Washington Street
Costal Road Repair starting Milling on Varney Mill rd., then to Middle St., then to Windjammer Way, Lark Street, Washington Street and finishing on Spruce Street.
Monday 10/12/26 through Friday 10/16/26
Start Shimming Varney Mill rd., then to Middle St., then to Windjammer Way, Lark Street, Washington Street and finishing on Spruce Street.
Start raising MH structures
Monday 10/19/26 through Friday 10/23/26
Finish raising MH structures
Start Surfacing Varney Mill rd., then to Middle St., then to Windjammer Way, Lark Street, Washington Street and finishing on Spruce Street.
Proposed Schedule for City of Bath – Street Paving – 2026-2027
Scope:
Lower and raise Manhole structures, mill 2” of existing pavement, shim to establish crown and cross-slope with 9.5 mm HMA, Surface with 1 ½ inches 12.5mm HMA
Monday 09/28/26 through Friday 10/02/26
Mobilize
Install traffic control
Lower MH on Windjammer Way, Middle Street, Lark Street
Monday 10/05/26 through Friday 10/09/26
Resume lowering MH on Spruce St. and Washington Street
Costal Road Repair starting Milling on Varney Mill rd., then to Middle St., then to Windjammer Way, Lark Street, Washington Street and finishing on Spruce Street.
Monday 10/12/26 through Friday 10/16/26
Start Shimming Varney Mill rd., then to Middle St., then to Windjammer Way, Lark Street, Washington Street and finishing on Spruce Street.
Start raising MH structures
Monday 10/19/26 through Friday 10/23/26
Finish raising MH structures
Start Surfacing Varney Mill rd., then to Middle St., then to Windjammer Way, Lark Street, Washington Street and finishing on Spruce Street.