Proposed Schedule for City of Bath – Street Paving – 2026-2027
Scope:
Lower and raise Manhole structures, mill 2” of existing pavement, shim to establish crown and cross-slope with 9.5 mm HMA, Surface with 1 ½ inches 12.5mm HMA
Monday 09/28/26 through Friday 10/02/26
- Mobilize
- Install traffic control
- Lower MH on Windjammer Way, Middle Street, Lark Street
Monday 10/05/26 through Friday 10/09/26
- Resume lowering MH on Spruce St. and Washington Street
- Costal Road Repair starting Milling on Varney Mill rd., then to Middle St., then to Windjammer Way, Lark Street, Washington Street and finishing on Spruce Street.
Monday 10/12/26 through Friday 10/16/26
- Start Shimming Varney Mill rd., then to Middle St., then to Windjammer Way, Lark Street, Washington Street and finishing on Spruce Street.
- Start raising MH structures
Monday 10/19/26 through Friday 10/23/26
- Finish raising MH structures
- Start Surfacing Varney Mill rd., then to Middle St., then to Windjammer Way, Lark Street, Washington Street and finishing on Spruce Street.
Monday 10/26/26 through Friday 10/30/26
- Finish installing surface
- Clean up and demobilize
Share Project Updates on Facebook
Share Project Updates on X (formerly Twitter)
Share Project Updates on Linkedin
Email Project Updates link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends