1. Washington Street (North of Harward St - 1500 ft. x 24 ft.): Remove 2-inches of existing pavement via cold-planing; shim to establish crown and cross-slope with 9.5 mm HMA; Surface with 1 ½ - inches 12.5 mm HMA.

2. Varney Mill Road (From North Bath Road - 1500 ft. x 24 ft.): Remove 2-inches of existing pavement via cold-planing; shim to establish crown and cross-slope with 9.5 mm HMA; Surface with 1 ½ - inches 12.5 mm HMA.

3. Spruce Street (Total with approximately 110' of Federal St) off of High St - 900 ft. x 21 ft.: Remove 2-inches of existing pavement via cold-planing; shim to establish crown and cross-slope with 9 .5 mm HMA; Surface with 1 ½ - inches 12.5 mm HMA. (Bid Alternate for 640' of slip form concrete curb)

4. Lark St. (Full length - 575 ft. x 24 ft.):Remove 2-inches of existing pavement via cold-planing; shim to establish crown and cross-slope with 9.5 mm HMA; Surface with 1 ½ - inches 12.5 mm HMA.

5. Middle St. (South of Leeman Hwy to South St- 1200 ft. x 24 ft.): Remove 2- inches of existing pavement via cold-planing; shim to establish crown and

cross-slope with 9.5 mm HMA; Surface with 1 ½- inches 12.5 mm HMA.

6. Windjammer Way;(North of North Street 525' x 24' and 275' x 40'): Remove 2- inches of existing pavement via cold-planing; Shim to establish crown and cross­slope with 9.5 mm HMA; Surface with 1 ½- inches 12.5mm HMA

1. Washington Street (North of Harward St - 1500 ft. x 24 ft.): Remove 2-inches of existing pavement via cold-planing; shim to establish crown and cross-slope with 9.5 mm HMA; Surface with 1 ½ - inches 12.5 mm HMA.

2. Varney Mill Road (From North Bath Road - 1500 ft. x 24 ft.): Remove 2-inches of existing pavement via cold-planing; shim to establish crown and cross-slope with 9.5 mm HMA; Surface with 1 ½ - inches 12.5 mm HMA.

3. Spruce Street (Total with approximately 110' of Federal St) off of High St - 900 ft. x 21 ft.: Remove 2-inches of existing pavement via cold-planing; shim to establish crown and cross-slope with 9 .5 mm HMA; Surface with 1 ½ - inches 12.5 mm HMA. (Bid Alternate for 640' of slip form concrete curb)

4. Lark St. (Full length - 575 ft. x 24 ft.):Remove 2-inches of existing pavement via cold-planing; shim to establish crown and cross-slope with 9.5 mm HMA; Surface with 1 ½ - inches 12.5 mm HMA.

5. Middle St. (South of Leeman Hwy to South St- 1200 ft. x 24 ft.): Remove 2- inches of existing pavement via cold-planing; shim to establish crown and

cross-slope with 9.5 mm HMA; Surface with 1 ½- inches 12.5 mm HMA.

6. Windjammer Way;(North of North Street 525' x 24' and 275' x 40'): Remove 2- inches of existing pavement via cold-planing; Shim to establish crown and cross­slope with 9.5 mm HMA; Surface with 1 ½- inches 12.5mm HMA

  • Project Updates

    Share Project Updates on Facebook Share Project Updates on X (formerly Twitter) Share Project Updates on Linkedin Email Project Updates link

    CCC Construction, LLC

    13 Callahan Drive, Augusta, Me. 04330, Tel: (207) 441-6087

    Proposed Schedule for City of Bath – Street Paving – 2026-2027

    Scope:


    Lower and raise Manhole structures, mill 2” of existing pavement, shim to establish crown and cross-slope with 9.5 mm HMA, Surface with 1 ½ inches 12.5mm HMA

    Monday 09/28/26 through Friday 10/02/26

    • Mobilize
    • Install traffic control
    • Lower MH on Windjammer Way, Middle Street, Lark Street

    Monday 10/05/26 through Friday 10/09/26

    • Resume lowering MH on Spruce St. and Washington Street
    • Costal Road Repair starting Milling on Varney Mill rd., then to Middle St., then to Windjammer Way, Lark Street, Washington Street and finishing on Spruce Street.

    Monday 10/12/26 through Friday 10/16/26

    • Start Shimming Varney Mill rd., then to Middle St., then to Windjammer Way, Lark Street, Washington Street and finishing on Spruce Street.
    • Start raising MH structures

    Monday 10/19/26 through Friday 10/23/26

    • Finish raising MH structures
    • Start Surfacing Varney Mill rd., then to Middle St., then to Windjammer Way, Lark Street, Washington Street and finishing on Spruce Street.

    Monday 10/26/26 through Friday 10/30/26

    • Finish installing surface
    • Clean up and demobilize

    CCC Construction, LLC

    13 Callahan Drive, Augusta, Me. 04330, Tel: (207) 441-6087

    Proposed Schedule for City of Bath – Street Paving – 2026-2027

    Scope:


    Lower and raise Manhole structures, mill 2” of existing pavement, shim to establish crown and cross-slope with 9.5 mm HMA, Surface with 1 ½ inches 12.5mm HMA

    Monday 09/28/26 through Friday 10/02/26

    • Mobilize
    • Install traffic control
    • Lower MH on Windjammer Way, Middle Street, Lark Street

    Monday 10/05/26 through Friday 10/09/26

    • Resume lowering MH on Spruce St. and Washington Street
    • Costal Road Repair starting Milling on Varney Mill rd., then to Middle St., then to Windjammer Way, Lark Street, Washington Street and finishing on Spruce Street.

    Monday 10/12/26 through Friday 10/16/26

    • Start Shimming Varney Mill rd., then to Middle St., then to Windjammer Way, Lark Street, Washington Street and finishing on Spruce Street.
    • Start raising MH structures

    Monday 10/19/26 through Friday 10/23/26

    • Finish raising MH structures
    • Start Surfacing Varney Mill rd., then to Middle St., then to Windjammer Way, Lark Street, Washington Street and finishing on Spruce Street.

    Monday 10/26/26 through Friday 10/30/26

    • Finish installing surface
    • Clean up and demobilize