Monthly Update - March 2026

Owner

  • Weekly Owner–Architect–Contractor (OAC) meetings continue to review project progress, coordination items, and outstanding action items.
  • The City continues coordinating with abutters and CMP regarding modifications needed to raise the overhead electrical services across the station’s curb cut.
  • Application for Payment No. 3 has been submitted by Benchmark and is currently under review by the project team and USDA representatives.

Design & Engineering

  • The design team continues reviewing contractor submittals and procurement documentation, withfocus on long-lead items and federal funding compliance.
  • The design team and contractor are addressing technical clarifications and field coordination items as construction progresses.
  • The Fire Department and City representatives continue to be consulted on relevant design items to ensure operational needs are incorporated.

Construction Activities

  • Ledge blasting operations within the building footprint, stormwater retention area, and select utility trench alignments have been completed.
  • Excavated ledge material is currently being processed on site and reused as structural fill within the building footprint, in accordance with project requirements.
  • Backfilling operations within the building footprint are approximately 75% complete to a point six (6) inches below the bottom of slab elevation.
  • Exterior concrete foundation work, including formwork, reinforcing steel placement, and concrete placement, is scheduled to commence on April 6, 2026.
  • Coordination with subcontractors and suppliers remains ongoing to support upcoming foundation and structural activities.
  • The project team continues to monitor site conditions, material placement, and compliance with project specifications during active earthwork and backfilling operations.
Share Monthly Update - March 2026 on Facebook Share Monthly Update - March 2026 on X (formerly Twitter) Share Monthly Update - March 2026 on Linkedin Email Monthly Update - March 2026 link