Monthly Construction Update-February 2026

- A Groundbreaking ceremony was held on January 28th.
- The OAC Meeting (Owner, Architect, Contractor) was established for every Wednesday at 2pm, initially virtual with a transition to onsite once job trailers are established with power and heat.
- The City pursued impacted residents to gain approval for needed CMP changes to accommodate raising the overhead power lines across the Station’s curb cut.
Design & Engineering
- The design team began reviewing submittals, with Benchmark providing priorities on long lead items.
- The Chief and City are being consulted on relevant submittals.
- Small changes are being documented in RFI responses or RFP issuance for pricing.
Construction Activities
- A Pre-Excavation Site Meeting was held on January 14th. Updates to the site management plan were made and documented.
- The Building Permit was issued on January 21st.
- Benchmark mobilized with site fence, initial excavation, etc.
|
Financial Status |
|
| Bond | $13,050,000 |
| CDS Funding | $2,289,308 |
| City TIF Funds | $1,738,376 |
| City Council approved additional TIF monies | $460,692 |
| City Council approved HMP funding | $1,000,000 |
Total Project Budget |
$18,538,376 |
| Anticipated Project Variance | $ .0 |
Share Monthly Construction Update-February 2026 on Facebook
Share Monthly Construction Update-February 2026 on Twitter
Share Monthly Construction Update-February 2026 on Linkedin
Email Monthly Construction Update-February 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends