Monthly Update - April 2026

Owner
- Weekly Owner–Architect–Contractor (OAC) meetings continue to review project progress, coordination items, and outstanding action items.
- The City continues coordinating with abutters and CMP regarding modifications to reconnect to elevated service. New poles and high voltage wires now installed.
- Application for Payment No. 4 has been submitted by Benchmark and is currently under review by the project team and USDA representatives.
Design & Engineering
- The design team continues reviewing contractor submittals and procurement documentation, with focus on long-lead items and federal funding compliance.
- The design team and contractor are addressing technical clarifications and field coordination items as construction progresses.
- The Fire Department and City representatives continue to be consulted on relevant design items to ensure operational needs are incorporated.
Construction Activities
- Ledge blasting operations within the building footprint, stormwater retention area, and select utility trench alignments have been completed.
- Excavated ledge material is currently being processed on site and reused as structural fill within the building footprint, in accordance with project requirements.
- Backfilling operations within the building footprint are approximately 85% complete to a point six (6) inches below the bottom of slab elevation. Backfilling of exterior foundation will be done when the wall is complete.
- Exterior concrete foundation work, including formwork, reinforcing steel placement, and concrete placement, footings 95% complete, rebar ting and forming for walls started 04/28/26
- Coordination with subcontractors and suppliers remains ongoing to support upcoming foundation, structural activities and underground utilities.
- The project team continues to monitor site conditions, material placement, testing and compliance with project specifications during active earthwork, backfilling and concrete operations.
Share Monthly Update - April 2026 on Facebook
Share Monthly Update - April 2026 on X (formerly Twitter)
Share Monthly Update - April 2026 on Linkedin
Email Monthly Update - April 2026 link
Thank you for your contribution!
Help us reach out to more people in the community