11/9/26 UPDATE:
11/9/26: Utility locating and surveying for the Richardson Street/Western Avenue project is complete. Next week, work crews will begin a mill and overlay of new asphalt on the portion of Richardson Street west of Lilac. One or more new speed tables will also be installed on Western Avenue. This work is expected to last approximately 2 weeks, at which point road construction will pause for the winter. Some off-road work to the storm drain pipelines may happen over the winter as weather and site conditions allow. Road work will resume in mid spring with the remainder of Richardson Street getting a full-depth reconstruction followed by the installation of more speed tables on Richardson and Western.
Share 11/9/26 UPDATE: on Facebook
Share 11/9/26 UPDATE: on X (formerly Twitter)
Share 11/9/26 UPDATE: on Linkedin
Email 11/9/26 UPDATE: link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends