Community Update - November 2026

Harward Street Pump Station & Sewer Interceptor Upgrade Project – Community Update November 2026

Work Completed Last Month

Construction activities resumed along Denny Road in early October following delivery and installation of a new temporary sheeting system needed to address challenging soil conditions encountered during sewer installation. Crooker Construction remobilized to the site on October 5 and has successfully resumed installation of the 36-inch sewer interceptor. The new sheeting system has been effective in stabilizing excavation areas, allowing work to progress through the difficult blue clay soils encountered in this section of the project. Initial paving was also completed on Washington Street, Park Street, and Winship Street.

At the pump station, mechanical demolition activities were completed, the flood wall coating was installed, and masonry work continued throughout the month. Preparations are also underway for upcoming structural beam installation and additional preparation for bypass pumping of the station.

What’s Next

Work on the 36-inch sewer interceptor will continue between Denny Road and Office Drive. Poor soil and base will result in some extended construction activity for this particular cross country section. The sewer bypass system remains in operation within the work area and will continue to be adjusted as needed to safely manage flows during construction and wet weather events. Cleanup, grading, and restoration activities will continue on Park Street, Winship Street, and other completed portions of the project as weather and construction sequencing allow.

At the pump station, masonry work is expected to wrap up while demolition, structural beam installation, and architectural upgrades continue. A 2-day shutdown of Washington Street between Harward and Park will happen early November so that work within the CSO manhole can be completed. Preparations are also being made for the pump station bypass, which is currently anticipated to begin in December.

Traffic & Neighborhood Impacts

Construction activities along Denny Road and High Street will continue to require traffic control measures. The project team reopened High Street once the work transitioned beyond the current construction zone, although future temporary closures will be required for upcoming water main work. Residents should continue to expect construction-related noise, truck traffic, equipment movement, and temporary traffic control within the active work areas.

The temporary construction access connection associated with Barque Road is no longer needed for current work activities and will be permanently shut down. The project team will continue coordinating with residents regarding access, restoration, landscaping, and other property-specific concerns throughout construction.

Looking Ahead

Construction of the Harward Street Pump Station & Sewer Interceptor Upgrade Project continues to progress, with the current contract schedule showing substantial completion anticipated in March 2027. The immediate focus will be continuing sewer interceptor installation towards and down Office Drive while advancing pump station construction and site restoration activities.

The City of Bath, Wright-Pierce, Crooker Construction, and the project team will continue working together to advance construction, coordinate upcoming work, minimize disruptions, and keep residents informed as the project progresses.