11/19/26 UPDATE:
LAST WEEK
Crews finished installing the curb along the south side of Elm Street. The McGee crew followed behind, smoothing and leveling the sidewalk area to get it ready for concrete.
THIS WEEK
Curb crews will install the curb along the north side of Elm Street. The McGee crew will follow behind, smoothing and leveling the sidewalk area. Once that is done, all the curbs and sidewalk areas will be ready for the next step.
WHAT’S NEXT: CONCRETE!
The next big step is installing the concrete portions of the new sidewalks.
The concrete crew is expected to arrive early this week, although the schedule could change. If everything stays on track, we are hopeful that concrete work can begin early in the week.
This work is weather dependent, so crews will be working to make the most of the remaining construction season.
Share 11/19/26 UPDATE: on Facebook
Share 11/19/26 UPDATE: on X (formerly Twitter)
Share 11/19/26 UPDATE: on Linkedin
Email 11/19/26 UPDATE: link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends